UPDF Reduces Shoddy Works in Katakwi District

By Our Reporter

 

KATAKWI

RDC Katakwi, Stephen Ilemukorit Okure pointing at the roof during the inspection of construction works at Katakwi General Hospital on Thursday. Credit by Delux Emmy Alomu

Officials in Katakwi District are optimistic that the prevalence of substandard work in health construction projects will decrease this financial year due to the significant role played by the Uganda Peoples Defense Forces (UPDF) Engineering Brigade.

 

This assurance was given during the third site meeting attended by district officials, the Ministry of Health, and the UPDF, focusing on the ongoing construction of a Shs1 billion state-of-the-art surgical theatre at Katakwi General Hospital.

 

The UPDF Engineering Brigade is currently spearheading the construction of the surgical theatre at Katakwi General Hospital, as well as a modern theatre at Toroma Health Centre IV, with an investment exceeding Shs500 million.

 

Additionally, they have secured contracts for building a Complex Out-Patient Department at Akurao Health Centre II, with an estimated cost of around Shs500 million, and undertaking renovation works at Ngariam Health Centre III, valued at over Shs370 million.

 

During the site meeting for the surgical theatre at Katakwi General Hospital on Thursday, Harriet Akwii, the Principal Assistant Secretary representing the Chief Administrative Officer, expressed confidence that this year will see far fewer construction challenges. She urged the UPDF Engineering Brigade to uphold the quality standards throughout the projects in the district.

 

Akwii emphasized that the purpose of the meeting was to assess progress, identify any obstacles, and strategize on solutions while ensuring that the project remains on schedule for completion.

 

Capt. Noah Opio, the UPDF Engineering Brigade’s Project Manager for the Eastern Region, reported that the surgical theatre is currently 70% complete. He noted that in addition to the regular inspections by district engineers and Ministry of Health representatives, community involvement is crucial. This is why local leaders and residents are invited to participate in routine site meetings, which are open to everyone.

 

Opio expressed concern that the one-year project timeline is expected to be condensed to just six months. With only electrical installation, plumbing, sealing, painting, and external door installation remaining, he highlighted the advantages of their team compared to civilian contractors. He noted that they prioritize quality over profit, lack political connections at the district level, maintain a clear command structure, supervise effectively, and source materials from verified suppliers.

 

Leonard Ekellot, a civil engineer from the district, acknowledged the army’s work, confirming that any minor defects identified are quickly addressed. Simon Okello, the senior environment officer, emphasized the importance of being attentive to social and environmental issues, particularly regarding tree planting.

 

Joseph Ecuman, Vice Chairperson of the District LCV, praised the engineering brigade’s efforts, stating that even the average person can recognize the quality of their work. He suggested that moving forward, all contracts should be awarded to the UPDF to avoid the challenges associated with tight financial year deadlines.

 

In closing the meeting, Stephen Ilemukorit Okure, the Resident District Commissioner for Katakwi, pointed out that many construction projects have stalled due to insufficient action from the LC-Vs and the CAO’s office. He urged them to take serious measures against negligent contractors.

 

He mentioned specific projects, like Getom Seed Secondary School, which was originally scheduled for completion in 14 months but has now extended to 36 months, causing delays in providing educational facilities for children. Other delayed projects, such as Okulonyo, Olilim Primary School, and Okore, have also failed to meet timelines, disappointing the community’s expectations for quality construction services.

 

The RDC called on the CAO’s office to review procurement processes and support the audit department in identifying substandard work promptly. He reiterated that quality is paramount for the UPDF, emphasizing their commitment to delivering value for money and completing projects on time. Ilemukorit declared that the ongoing delays in construction are unacceptable and instructed the CAO to ensure no projects proceed under such circumstances.

 

President Museveni consistently commends the UPDF Engineering Brigade for their efficient and cost-effective construction of government projects, urging ministries like Health and Education to utilize them to reduce contractor expenses and combat corruption, as their capabilities are essential for developing infrastructure such as hospitals, schools, and military facilities, including significant projects like the Standard Gauge Railway.

 